Data Loading...
Barbirolli Square, Manchester
171 Downloads
10.91 MB
Twitter Facebook LinkedIn Copy link
RECOMMEND FLIP-BOOKS
Central Square
MotaEngil-Africa Nsika Architecture & Design is a boutique architectural prac- tice that specialises
Central Square
Central Square 4 CENTRAL SQUARE SANDTON 5 Sandton’s urban centre stage 6 CENTRAL SQUARE SANDTON 7 On
Apollo Square
Apollo Square A P O L L O S QUA R E AS EFFORTLESS LIVING IN THE HEART OF HOLLADAY
Apollo Square - Features
Apollo Square - Features A P O L L O S QUA R E BUILDING FEATURES Nature and science blend seamlessly
Crown Street Manchester
Crown Street Manchester TWO AND THREE BEDROOM APARTMENTS AND PENTHOUSES WWW . C R O W N S T R E E T
Hardware Brochure - Europoint Manchester
Hardware Brochure - Europoint Manchester PRINTERS • CUTTERS • LAMINATORS HARDWARE EUROPOINT At EUROP
Dukes, Eaton Square - Bursar
CFO. • A minimum of a degree level qualification (or equivalent), ideally with a professional qualif
Deansgate Square East Tower
Deansgate Square East Tower E A S T T O W E R Deansgate S Q U A R E A N E W
2218 Madison Square Listing
Co-op Fees - Compass Type Single Family # Bathrooms Full 1 MLS Type - # Bathrooms Half Year Built -
Deansgate Square South Tower
Deansgate Square South Tower S O U T H T O W E R Deansgate S Q U A R E A N E
100 Barbirolli Square, Manchester £19m Cat A+ Refurbishment
100 BARBIROLLI SQ
CLIENT: AEW Europe PM & QS: Savills ARCHITECTS: 5Plus Architects M&E CONSULTANTS: MZA
SIZE: 180,000ft 2 PROGRAMME: 78 weeks VALUE: £19M
Following the successful completion of 101 Barbirolli Square, Savills and AEW Europe then negotiated 100 Barbirolli through a 2-stage process under the JCT Standard Form of Contract with CDP portions. Through the early stages of the design development Ardmac was engaged to produce a cost plan, risk management plan, input on buildability, logistics, programming and VEing until RIBA Stage 4 where a fixed price was agreed. The major Cat A+ refurbishment project included the construction of an additional 11 th floor to the building and the infill of 50% of the 11-storey atrium to create additional ‘net’ floor area space.
The newly formed atrium was then clad with a Schuco glazed curtain walling system with a new bespoke manufactured glazed roof.
The high end fit-out works included all new state-of- the-art MEP including ‘Environmental Automatic Solar Dimming LED Lighting’, BMS and all new exposed services together with the complete refurbishment of the 11-storey building. The newly extended two-storey reception entrance included new curtain walling which created a stylish ‘grander’ entrance to the high end sophisticated new reception area.
On this challenging redevelopment project, it was mission critical that we could rely on a contractor that would pro-actively lead and deliver our challenging project to a superior standard. During tender process we were impressed with Ardmac’s professionalism and attention to detail throughout the whole process and preparation of the construction site and proposed works. We therefore selected them to run our exciting and challenging development project given they outperformed their peers and competitors. During the project and to date, we have been consistently impressed with the proactive nature of the Ardmac project team, quality of the construction and the delivery of the design team’s vision, to be critically on time and on budget. - Director - AEW Europe
PROGRESS - MARCH
The progress image above shows the steel frame constructon of the tenth floor. Below shows the installed rooflight that sits on top of the completed tenth floor.
PROGRESS - NOVEMBER
MARCH 2020 PROGRESS
NOVEMBER 2020 PROGRESS
WATCH VIDEO:
COMPLETED PROJECT
COMPLETED PROJECT